HLA Project No. 10073C
Williams Charles West Construction of Kennewick, Washington, is under contract to replace the
mechanisms in the north and south clarifiers at the main wastewater treatment plant.
Equipment delivery began the week of June 18, 2012. WWTP staff began draining the south
clarifier on June 16 in anticipation of the installation.
The contractor is progressing with the work
on the south clarifier and expects to have the clarifier back in operation by the end of July 2012. Work
effort will then switch to the north clarifier and the installation should be completed by the end of
August.
October Update
New photos of construction progess on the Clarifier Project.
*Insert photos from rotator of Clarifier construction*